icrn phw energy cse dte gobar times rwh csestore iep
Green Clearance Watch
A public information system to track and analyse green clearances since 2007
OUR PARTNERS | ABOUT US | CONTACT US
THERMAL POWER PLANT
CEMENT
IRON & STEEL
NUCLEAR POWER PLANT
COAL MINING
HYDROPOWER
OTHER MINERALS
BAUXITE MINING
IRON ORE MINING
LIMESTONE MINING
PORT
Sector : Cement
Environment Clearance | Forest Clearance

Javascript is required to view this map.
List of Companies
Facts
Sector
Cement
NO. OF PROJECTS CLEARED
168
TOTAL LAND REQUIRED (ha.)
17737.86
TOTAL WATER REQUIRED (m3/day)
327728.77
TOTAL CAPACITY
301.08 MTPA
Sector Details
INSTALLED CAPACITY OF CEMENT IN INDIA AT THE END OF 10TH FYP (2006-07):
179 MTPA
TARGET CAPACITY FOR 11TH FYP:
236 MTPA
INSTALLED CAPACITY OF CEMENT IN INDIA IN 2009-10:
263 MTPA
COMBINED CAPACITY OF CEMENT (EXISTING AND GRANTED) AT THE END OF 11TH FYP:
369 MTPA
PRODUCTION OF CEMENT IN INDIA IN 2009-10:
201 MTPA
MAXIMUM CEMENT PLANT CAPACITY GRANTED CLEARANCE IN A STATE (2007-AUGUST 2011):
41.2 MTPA IN ADNHRA PRADESH
MAXIMUM CEMENT PLANT CAPACITY GRANTED CLEARANCE IN A DISTRICT (2007-AUGUST 2011):
23.3 MTPA IN GULBARGA, KARNATAKA